Transitional HousingCompleted Transitional Housing Projects

Transitional Housing Project at "TranquilTrees Living" Former Wing On School

Location and Environment

Details

Project Name "TranquilTrees Living" Former Wing On School
Operating Organisation Hong Kong Youth Affairs Development Foundation
Location Tai Shu Ha Road West, Yuen Long
No. of Units and Households 261 units and approximately 523 residents
Project Data
  • Converted and newly-built project
  • Conversion of 1 no. single-storey building and construction of 1 no. three-storey to four-storey building
  • 21 nos. 1-person units
  • 218 nos. 1/2-person units
  • 21 nos. 3-person units
  • 1 no. 2/3-person barrier free unit
Provisions Each unit will be equipped with a bathroom with toilet and a cooking area.
Funding Scheme Funding Scheme to Support Transitional Housing Projects by Non-government Organisations
(A grant of $143.55 million has been approved.)
Date of Commencement of Works August 2023
Date of Completion December 2024
Date of Intake End-December 2024
Operation Period Planned to operate for not less than 5 years

*Noteļ¼š

1. The operating organisation may from time to time update or change the information of the project, including the eligibility criteria for application, rent level and related services. For latest information of the project, please visit the project website or contact the operating organisation.

2. All map coordinates are indicative only and do not reflect the exact locations.

3. The projects are at different development stages, namely:
(i) local consultation has commenced with the project details to be confirmed;
(ii) procurement process for the consultancy team has commenced; and
(iii) procurement process for the works contract has commenced.