As one of the batches of transitional housing projects adopting the Modular Integrated Construction (MiC) method, Sheung On Street project will provide a modular housing block of four storeys upon completion. MiC method shortens construction time and reduces the number of on-site workers.
Project Name | "Everest Residence" at Sheung On Street, Chai Wan |
---|---|
Operating Organisation | The Society for Community Organization Limited |
Location | Sheung On Street, Chai Wan |
No. of Units and Households | 103 units and approximately 210 residents |
Project Data |
|
Provisions | Each unit will be equipped with a bathroom with toilet and a cooking area. |
Funding Scheme | Funding Scheme to Support Transitional Housing Projects by Non-government
Organisations (A grant of $56.65 million has been approved.) |
Date of Commencement of Works | December 2022 |
Date of Completion | April 2024 |
Operation Period | About 5 years |
September 2021 |
Pre-construction Preparation
Photomontage ![]() G/F Layout Plan ![]() 1/F-3/F Layout Plan ![]() |
---|---|
January 2023 |
Works Commencement Ceremony
Ground-breaking Ceremony officiated by Winnie Ho, Secretary for Housing and Victor Tai, Under Secretary for Housing ![]() ![]() ![]() |
*Noteļ¼ 1. The operating organisation may from time to time update or change the information of the project, including the eligibility criteria for application, rent level and related services. For latest information of the project, please visit the project website or contact the operating organisation. 2. All map coordinates are indicative only and do not reflect the exact locations. |