Completed Transitional Housing Projects| Project Name | Pok Oi Sing Ping Village |
|---|---|
| Operating Organisation | Pok Oi Hospital |
| Location | 200 Ping Che Road, Ta Kwu Ling (Former Sing Ping School) |
| No. of Units and Households | 601 units and about 1000 residents(Project has been negotiated with stakeholders for the launch.) |
| Project Data |
|
| Provisions | Each unit is equipped with a bathroom with toilet and a cooking area. |
| Funding Scheme | Funding Scheme to Support Transitional Housing Projects by Non-government
Organisations (A grant of $336.74 million has been approved.) |
| Date of Commencement of Works | November 2022 |
| Date of Completion | July 2024 |
| Date of Intake | August 2024 | Operation Period | Estimated to be not less than 5 years |
| Environment, features, floor/ layout plans, show flats and etc. |
Project layout plan ![]() Bird’s eye view ![]() Sample units Sample kitchen Sample toilet Layout of 1-2 person units ![]() Layout of 3-4 person units ![]() Layout of 5-6 person units or barrier-free units ![]() |